Boot sequence Catalyst 6509 modules

vanderpal.m
Level 1
Level 1

Hi!

Is it possible to configure the boot sequence of the modules in a 6509 chassis? I want to make sure that the STP via the fiber connections have converged before the server connections on another module have their links up.

E.g. module 7 and 8 are booted first, and module 1 is booted one minute later.

Best regards,

Marco

2 Replies 2

glen.grant
VIP Alumni
VIP Alumni

I have never heard of anything like this .

Jon Marshall
Hall of Fame
Hall of Fame

Hi

Like Glen i have not heard of being able to do this either.

One rather obvious solution although i'm not sure how easy it would be for you to do is to move the modules around within the 6500.

HTH

Jon