Amit Singh Fri, 04/20/2007 - 23:37
User Badges:
  • Cisco Employee,

The best design practice is using 2 fibers/ethernet links from each edge switch and connect the links to each 6500 at the core.Connect inturn both the 6500 to make a traingle. Use the PVST and MHSRP to do the STP load-balancing and L3 traffic load-balancing using MHSRP.


Another option would be to run connect both the edge switches and then inturn run a single link from each edge switch to connect to each core 6500.Again run the STP and MHSRP load-balancing at the core.


HTH,Please rate if it does.


-amit singh

cfajardo1_2 Sat, 04/21/2007 - 06:21
User Badges:

is it possible for you to give me a sample config of both the core switches, configured for a single floor having 2 edge switches.


thanks