05-30-2007 09:33 AM
I am working on a project to move a MDS 9509 switch running version 3.0(2a). The switch is the primary of a redundant pair. We are making room for SAN expansion. I just wanted some advise on the move. So far I have completed the following:
wr mem
copy runn
map ports to servers (spreadsheet)
map ports to SAN (spreadsheet)
My basic project calls for:
wr mem
power down
remove fiber connections
move sw
power up
recable
What am I missing?
05-30-2007 04:27 PM
Biggest risk is you introduce new cables that have not been tested and turn out to be poor quality. Bit errors can easily lead to FC link failure or slow performance. Make sure you use known good working fiber cables in the location. Resuse existing cables if you can. If not, clearly mark any brand new cables, just in case you have an issue you can see if it coincides with the new cables.
05-30-2007 07:46 PM
You need to edit your list also.
Write mem is depricated, use copy run start.
Also, assuming this is an A / B fabric you need to ensure that you quiese the fabric you are moving first before shutting anything down. This will ensure the least possible disruption in your move.