Hi,
Is there a way to upgrade unity from Upgrading 4.0(4) to 4.2(1) with failover without having to take down the service?
07-01-2007 02:03 PM
You start the upgrade on primary server and at some point you have to start upgrade on secondary server. So at some point during the upgrade, both servers will be out of service. Also when the primary is being upgraded, secondary cannot accept voice messages. Check this link.
HTH
Sankar
PS: please rememeber to rate posts!
07-01-2007 02:26 PM
See this White Paper
Doing a Rolling Upgrade to Cisco Unity 5.0 with Failover Configured (With Microsoft Exchange)
http://www.cisco.com/en/US/docs/voice_ip_comm/unity/white/paper/50curollupgrade.html