We have a UCC Express with the server above. Now we need to upgrade to a bigger server due to a contact center expansion.

I did not find any document in Cisco.com about this subject.

I have this problem too.
0 votes
  • 1
  • 2
  • 3
  • 4
  • 5
Overall Rating: 3 (1 ratings)
Loading.
antonio.vazquez Wed, 10/24/2007 - 06:10

Hi,

I think, that you should export the configuration from the old server 7825-I2 and import that configuration in the new server (7835) using BARS application. Really, it's a software reinstallation.

Regards.

pfavamedidata Wed, 10/24/2007 - 06:21

I will use the MCS-7835-I2-CCX1.

It will be a hardware migration followed by 18 seats add-on, but the seats add-on is not a problem.

antonio.vazquez Wed, 10/24/2007 - 08:04

Hi,

then you should install the software in the new server and restore a backup from the old server using BARS like I tell you in a my last post. I supose that you'll install the same software version in the new and in the old servers, won't you?

If my message helps you please rate it.

Regards

Antonio