05-10-2008 11:18 PM
Hi,
I'm using LMS2.6 with CM4.0.10. From last week the UT Acquisition schedule process showing in running state continuously for more than 24 hours. We are having nearly 4500 end hosts.
[Previously it used to take 30 min (LMS2.5), from last one/two months it was taking 2 hours.]
I have restarted the server but still same problem. All processes seems to running normal.
Can anyone help please..
Regards,
Solved! Go to Solution.
05-11-2008 09:58 PM
No. The DCR data is stored in the cmf database. You will only lose Campus Manager-related data.
05-10-2008 11:25 PM
Please post the output of the pdshow command as well as the ut.log.
05-10-2008 11:33 PM
05-11-2008 10:19 AM
There appears to be a problem with the ANI database. If you have a known good LMS backup, it might be time to restore it. Else, you will need to reinitialize the ANI database then run a new Campus Data Collection, then a new UT acquisition. To reinitialize the ANI database, run the command:
C:\PROGRA~1\CSCOpx\bin\perl C:\PROGRA~1\CSCOpx\bin\dbRestoreOrig.pl dsn=ani dmprefix=ANI
05-11-2008 09:41 PM
Hi Clarke,
By reinitializing the ANI database do I lose DCR data?
Regards,
05-11-2008 09:58 PM
No. The DCR data is stored in the cmf database. You will only lose Campus Manager-related data.
05-11-2008 10:03 PM
Thank you Clarke...
05-11-2008 10:11 PM
Hi,
Daemon manager is running ...
Daemon manager must be shut down before running dbRestoreOrig.pl
Whats the next step?
05-11-2008 10:14 PM
net stop crmdmgtd
(reinitialize the database)
net start crmdmgtd