Just curious if anyone has upgraded a PG from ICM 6 to 7.2.4 with a CVP 3.1 PIM. If so, any gotchas that you came across while doing so. I'm confident I have my bases covered but it's always nice to know about the 'unknown'. Thanks!

1 Accepted Solution

Accepted Solutions

Riccardo Bua
Level 5
Level 5

There haven't been changes on the GED 125 side in the PIM for those releases, so no issues are/would be expected.

Regards,

Riccardo

View solution in original post

3 Replies 3

geoff
Level 10
Level 10

Pretty close. We upgraded a customer a couple of weeks ago from ICM 6.0 to ICM 7.2(4) and had CVP 3.0 SR1 in place. No changes yet to CVP. No issues at this stage.

Regards,

Geoff

Riccardo Bua
Level 5
Level 5

There haven't been changes on the GED 125 side in the PIM for those releases, so no issues are/would be expected.

Regards,

Riccardo

Riccardo,

Would you expect this to work fine with 7.2(5) aswell? I would think that it would?

Thanks so much!

Chad