02-27-2009 03:47 AM - edited 03-15-2019 04:30 PM
I`m due to upgrade a CUCM 6.X server to 6.1. and I`m querying a procedure
Current set up
Publisher - Running as Glass House- No CM Services, No TFTP etc
Subscriber
2x TFTP Servers
I know we upgrade to an inactive partition so not to effect production however due to various reasons I would like to do the following
Pull Disks on Pub to ensure we have a physical roll back option- test each disk in turn
Change Pub to allow the test phones to register to it
Upgrade Pub on Inactive Partition
Allow test phones to register to Pub - make test calls, access Admin , EM testing etc
Question
As the phones will reboot and so query the TFTP`s which I have not upgraded to the newer SW, it will then register to the Pub which is now on the newer SW- will this work or will it be a conflict between the Pub being on the newer SW and the TFTP being on the older version ?
or should I manually reconfigure the test phones only to use one of the TFTP Servers and the upgrade the same TFTP after I`ve done the Pub and reboot both- PUB and TFTP on the newer SW
Once I`m happy we will then upgrade the other TFTP followed by the Subs
Any thoughts or opinions
thanks
02-27-2009 04:08 AM
If by this:
Change Pub to allow the test phones to register to it
Upgrade Pub on Inactive Partition
you mean switch version on PUB and then upgrade SUBs (no switch version, but install upgrade) that's wrong
this applies to any linux upgrade:
Upgrading from Unified CM 5.x to Unified CM 6.x
http://www.cisco.com/en/US/docs/voice_ip_comm/cucm/srnd/6x/callpros.html#wp1043707
HTH
java
if this helps, please rate
02-27-2009 04:49 AM
Java
I mean to use the Pub as a quick test and if successful then upgrade and switch on the remaining Subs.
If the upgrade test is not good then re-insert the disks and reboot Pub /TFTP or just switch back on the Pub
02-27-2009 05:03 AM
the thing is that even if it's successful you'll need to switch back before upgrading the SUBs, if you leave PUB on 6.1(2) for testing and the SUBs in 6.1(1) and then try to upgrade you won't be able to do so
that's why the instructions clearly say to install the upgrade in all servers at a time, then switch one at a time
HTH
java
if this helps, please rate
02-27-2009 06:03 AM
Java
the reason I`m asking if that we had a failure when reverting back to the lower SW in our test lab so the idea is to the test the roll back on the Pub only first in case the lab and production Cluster are any way differetn though they are on the SW level. Would not the switch back to the Pub to the lower SW so the cluster is now all on the same Verison and then upgrade the Subs- once all done then switch one by one as per doc?- would this not work