08-15-2009 06:04 AM - edited 03-06-2019 07:15 AM
Folks, I understand that Maxage is the time a given switch will wait to hear BDPU's before it decides to elect root port. That said, I would answer e) for the question below. The correct answer according to the book is b). I can't understand why the Maxage time in this case is on the root bridge though. If the root bridge may even be down in this scenario why not consider the Maxage at the non-root switch?
1) Assume that a non-root
802.1d switch has ceased
to receive Hello BPDus.
Which SP setting determines
how long a non-root switch
waits before trying to choose
a new Root Port?
a) Hello time setting on the root
b) Maxage timer setting on the root
c) Forwrd Delay timer setting on the Root
d) Hello timer setting on the non-root switch
e) Maxage timer setting on the non-root switch
Solved! Go to Solution.
08-15-2009 08:17 AM
Marlon
The answer is b) because the timers that are used by all switches are the root bridge timers and not the local switch timers.
So prior to the loss of the BPDUs all switches would have received BPDUs from the root bridge and used the timers that the root bridge announced. If the root bridge goes down the timers learnt from the root bridge are still used.
Jon
08-15-2009 08:17 AM
Marlon
The answer is b) because the timers that are used by all switches are the root bridge timers and not the local switch timers.
So prior to the loss of the BPDUs all switches would have received BPDUs from the root bridge and used the timers that the root bridge announced. If the root bridge goes down the timers learnt from the root bridge are still used.
Jon
08-15-2009 02:16 PM
Oh!! Thanks.