Im running 2 UCCX servers (version 5) in High Availability.

To Failover all services from one server (the master) to the second server (slave), what is the best way to do it? I always go and reboot the Master server to be able to failover. There should be some way without rebooting the server.

Jay

I have this problem too.
0 votes
  • 1
  • 2
  • 3
  • 4
  • 5
Overall Rating: 0 (4 ratings)
Loading.
safety2008 Fri, 10/02/2009 - 03:49

I stop node manager in services. this causes failover and master becomes slave.

hth

Jayd000007 Fri, 10/02/2009 - 05:43

From services, STOP the "CRS Node Manager".

That is better alternativ than rebooting.