Unity 4 to Unity 7 parallel build/ User Migration

Mike Lydick
Level 1
Level 1

Unity 4 to Unity 7 parallel build

From the documentation, Cobras will not migrate users on an existing Unity UM to a new Unity System. So would the best process be to migrate just the subscribers with GSM and then do the Cobras import. The later is to allow for the 'extra' data to migrated to the subscribers, suchas zero-out to operator or other numbers? Based on this process how reliable will the migration be or should DIRT be considered the better tool?

1 Reply 1

lindborg
Cisco Employee
Cisco Employee

Moving with GSM and a follow up with COBRAS will work fine and will allow you to move groups of users while both systems are up and running as you go.

DiRT will get a bit more data (COS objects, templates, name lookup handlers of note) - but it requires the same version as the backup and it does a complete DB replacement.

More folks are using GSM or GSM with COBRAS follow up of late than DiRT for this reason - smaller sites that don't have a lot of handlers and don't use notification devices etc... just use GSM alone. A COBRAS follow up will get all your call handlers, schedules, interviewers, extra subscriber data and distribution lists as well so if those things are important to you, it's worth the extra step.