FWSM on VSS, interchassis link.

Unanswered Question

Capacity planning for interchassis links is an important part of VSS deployment. Include capacity for FWSM failover pairs to account for failover/state VLAN links between the two chassis if FWSM interchassis failover is deployed. It is recommended to set aside 1-2Gbps for this purpose.

Now, I'm using two 10Gb interface for VSL.

May I use two 1Gb interface, always on SUP720 to build a dedicated GEC for failover pairs only?

Thanks.

Andrea

I have this problem too.
0 votes
  • 1
  • 2
  • 3
  • 4
  • 5
Overall Rating: 0 (0 ratings)
Loading.
e-chuah Wed, 12/02/2009 - 00:59

Hi..

I don't think u can use the 1G link in the Sup720 to build a GEC for the failover pair.

THis is because the entire VSS is treated as one switch. If u connect the GE port in Switch1 to Switch2,

from VSS perspective, u are looping back the connection to itself.

Rgds

Eng Wee