03-03-2010 07:23 AM
Hi all,
At this moment I am installing 2 Cisco Catalyst 2960G-48TC-L switches with IOS 12.2(35)SE5 in an A330 aircraft instrumented for flight test.
I have noticed that it takes 3 minutes to start up the swiches, which is too much for my application. Therefore, I would like to reduce start-up time by means of disabling the POST, or at least taking it to the minimum.
POST process "PortASIC CAM Subsystem Tests" takes about 1:30 minutes to be done, which is 50% time consuming. So, I would like to disable this process and, if possible, any other unnecessary processes.
Thanks a lot.
03-03-2010 07:46 AM
It is not possible to do so.
If you want Avionics Ethernet (AFDX), talk to one of the existing manufacturers.
03-03-2010 07:54 AM
Hi,
I don't need AFDX. I am using an standard Ethernet network. In the past I have used Catalyst 2950, which has done its job pretty well. Nevertheless, it is no longer supported so I purchased a 2960. I would like 2960 to start upas fast as 2950 did.
Best Regards,