LMS 3.2/ Hum 1.2 - Duplicate job views completed

Answered Question
May 28th, 2010
User Badges:

Hello,

Does anybody has already saw that this default under a bug ?

It concerns Hum 1.2 /LMS 3.2


In the Current Admin/System preferences settings in HUM , the quick report job type "Interface avalaibility" is enable, every hour..


In the Common Services Job , recently completed, 2 jobs have been instancied , at same time, for this quick report.


Thanks

Richard.

Correct Answer by Joe Clarke about 6 years 11 months ago

From the server's command line, run:


NMSROOT/bin/cwjava -cw NMSROOT com.cisco.nm.cmf.jrm.jobcli


From the jobcli prompt, type:


delete 4298


Then exit the jobcli interface, and restart Daemon Manager.  The job should be gone.

  • 1
  • 2
  • 3
  • 4
  • 5
Overall Rating: 5 (1 ratings)
Loading.
Joe Clarke Sun, 05/30/2010 - 10:41
User Badges:
  • Cisco Employee,
  • Hall of Fame,

    Founding Member

Post a screenshot illustrating what you are seeing.

richard.tetu Tue, 06/01/2010 - 06:12
User Badges:

Hello, Joe,


Please see hereafter an example of  screenshots, taken.

In this example, it's for threshold violations.


I have remarked the same issue for others jobs launched, like in my first remark.



Thanks

Richard

Correct Answer
Joe Clarke Tue, 06/01/2010 - 10:25
User Badges:
  • Cisco Employee,
  • Hall of Fame,

    Founding Member

From the server's command line, run:


NMSROOT/bin/cwjava -cw NMSROOT com.cisco.nm.cmf.jrm.jobcli


From the jobcli prompt, type:


delete 4298


Then exit the jobcli interface, and restart Daemon Manager.  The job should be gone.

richard.tetu Wed, 06/02/2010 - 04:55
User Badges:

Hello,


Thanks for this answer.


Question: does it works for LMS 2.6 ?


Richard

richard.tetu Wed, 06/02/2010 - 07:01
User Badges:

Sorry, I did a research on the CISCO support web site , i found that it worked too for LMS 2.6 thanks.


Richard

Joe Clarke Wed, 06/02/2010 - 07:47
User Badges:
  • Cisco Employee,
  • Hall of Fame,

    Founding Member

Yes it does, but HUM doesn't exist in 2.6.  Deleting jobs using this interface should only be done as a last resort if the jobs cannot be removed from the GUI directly.