I have two 3750 stacks that are currently connected using two1GB fiber connections in an etherchannel. I now added new switches to each stack with 10GB modules in them. We would like to bring up the 10GB connection, but still have one of the 1GB lines as a backup, or even the whole etherchannel. Is there a way for us to make the 10GB the main and the 1GB the standby?

3 Replies 3

Sergey Fer
Level 1
Level 1

Sure. It is called Spanning-tree Protocol MSTP is a best way, I think. There are many other ways to do it, including L3 dynamic routing.

Devavrat Oka
Level 1
Level 1

STP would prefer the links based on cost calculation.

If these are L3 links, then use routing for failover.

Joseph W. Doherty
Hall of Fame
Hall of Fame

Disclaimer

The   Author of this posting offers the information contained within this   posting without consideration and with the reader's understanding that   there's no implied or expressed suitability or fitness for any purpose.   Information provided is for informational purposes only and should not   be construed as rendering professional advice of any kind. Usage of  this  posting's information is solely at reader's own risk.

Liability Disclaimer

In   no event shall Author be liable for any damages whatsoever (including,   without limitation, damages for loss of use, data or profit) arising  out  of the use or inability to use the posting's information even if  Author  has been advised of the possibility of such damage.

Posting

STP and routing are the "usual suspects", but another L2 option might be Flex Links.