I have a few questions I want to confirm:


We have CCM 6.1(4) in our cluster that we will soon be upgraded to CCM 8.0(3a).


  1. First I want to install CCM 8.0(3a) into the inactive partition on all CCM servers without switching the version (or rebooting the server).  I will do the version switch on a seperate day.  Is that possible?


   2. I have the CCM 8.X software feature licence.  Do I need to install this license before I install CCM 8.0(3a) into the inactive partition or can I do that         before I do a "Switch Version"?


   3.  I'm assuming no additional licensing is needed for our device units right?


Thank you!


-rya

Correct Answer by Rob Huffman about 5 years 2 months ago

Hey Rya,


Yes, you can upgrade into the inactive partition and do the switch-version at a later

time. You will need to track any changes that are made to the db between the upgrade time

and the switch-version to redo them after the final step


The 8.x Software feature license will be added after the switch-version is completed.


All node and DLU licenses will be migrated during the upgrade.


The upgrade from 6.1(4) to 8.0(3) is a direct upgrade path as shown;


Check out Table 8:


http://www.cisco.com/en/US/docs/voice_ip_comm/cucm/compat/ccmcompmatr1.pdf


Cheers!

Rob




"Show a little faith, there's magic in the night" - Springsteen

  • 1
  • 2
  • 3
  • 4
  • 5
Overall Rating: 5 (1 ratings)
Loading.
Correct Answer
Rob Huffman Fri, 06/01/2012 - 05:22
User Badges:
  • Super Red, 40000 points or more
  • Hall of Fame,

    Founding Member

  • Cisco Designated VIP,

    2017 IP Telephony, Unified Communications

Hey Rya,


Yes, you can upgrade into the inactive partition and do the switch-version at a later

time. You will need to track any changes that are made to the db between the upgrade time

and the switch-version to redo them after the final step


The 8.x Software feature license will be added after the switch-version is completed.


All node and DLU licenses will be migrated during the upgrade.


The upgrade from 6.1(4) to 8.0(3) is a direct upgrade path as shown;


Check out Table 8:


http://www.cisco.com/en/US/docs/voice_ip_comm/cucm/compat/ccmcompmatr1.pdf