CPO scheduled process always "missed"

davshapi
Level 1
Level 1

CPO 3.1.1.87

I have a process with a simple schedule that is always registering as "missed". The process can run if I kick it off manually.

Daily

9am

Repeat 135x every 4 minutes

No other conditions

1 Accepted Solution

Accepted Solutions

Shaun Roberts
Cisco Employee
Cisco Employee

It should be running. There has always been a funky UI issue around showing missed versus not.

Especially if you are not archiving the process.

Do you archive the process after each run?

--Shaun Roberts
Principal Engineer, CX
shaurobe@cisco.com

View solution in original post

4 Replies 4

Shaun Roberts
Cisco Employee
Cisco Employee

It should be running. There has always been a funky UI issue around showing missed versus not.

Especially if you are not archiving the process.

Do you archive the process after each run?

--Shaun Roberts
Principal Engineer, CX
shaurobe@cisco.com

I will check. We have some high volume processes so archiving might be turned off. That is set on a per-process basis, correct? 

Yes correct. It's per-process.

You can run this query to find all processes that have archiving disabled. (at least it worked last time I used it)

select * from dbo.Configuration where ConfigurationData.value('(ProcessConfiguration/StoreWhenCompleted)[1]',
'nvarchar(max)') = 'false';
--Shaun Roberts
Principal Engineer, CX
shaurobe@cisco.com

Archiving was enabled. However I deleted the automation pack and imported a newer version and it seems to be working now. The world may never know. Thanks! 