3750 StackWise cables hot swappable?

anowell
Level 1
Level 1

I have a stack of 3750's that have their StackWise cables in the wrong order. Do I need to power off the switches to rearrange the StackWise cables?

Thanks in advance!

2 Replies 2

amit-singh
Level 8
Level 8

Hi Friend,

It is always suggested to remove the switches that you want to disconnect from the stack. Taking the stackiwise cable out from the switch stack can result a single stack to be divided into two and can result in different problems.

I would suggest to power off the stack and then power on the Stack master first and then rest of the switches.

http://www.cisco.com/univercd/cc/td/doc/product/lan/cat3750/12225sed/scg/swstack.htm#wp1156338

HTH, Please rate if it does.

-amit singh

Thank you so much for the fast response!