05-31-2010 07:47 PM - edited 03-06-2019 11:21 AM
Hi,
I would like to know what is the best practice to shutdown 6509s and 3750 stack switch
during a power shutdown.
In the past what I did was :-
i) Backup all the configuration on the 3750s and the 6509s including the FWSM context on the 6509s.
ii) Tun off the power on the box.
iii) When the power upgrade is done, turn back the power of the machine and make sure
the interfaces on the devices are up and running.
Is the steps listed considered standard practice or is there any other things that I could do to make this
better ?
Pls advice,
Cheers
SN.
Solved! Go to Solution.
05-31-2010 08:01 PM
05-31-2010 08:01 PM
Hi SN,
The steps you are following are good to go.
Good Luck
Reza