New Member

CCM Ver 6 - scheduled back stopped working

We are running System version: 6.0.1.2000-3

We have in the disater recovery section configured a backup job to backup to a network drive

The backup was configured to do weekly and we started it on july 1 2008.

It backed up regularlly till 8/19/2008.

We did not stop the backup job but since that date (8/19) it has not ran.

Checking the hitory only shows the good jobs and I cannot seem to find why it stopped.

As anyone else seen this ?

2 REPLIES
Silver

Re: CCM Ver 6 - scheduled back stopped working

Not something I've seen before but it may be an unrelated problem with CCM.

Have you checked the network drive/folder to make sure there are no disk space issues as it may have reached capacity, hence the reason the backup is failing (or there are disk quota's in place)?

Then just try a manual backup to test...

Please rate useful posts....

New Member

Re: CCM Ver 6 - scheduled back stopped working

The network drive has over 1 tera on it. I disabled the schedule and re-enabled it and last nights backuop ran fine. It must be one of those "Werid" cisco things.

but its working again

135