We just received a Catalyst 6509 with two WS-sup720 supervisor engines. I'm just wondering of any any gotchas before we put this switch into production.

thanks.

1 Reply 1

thisisshanky
Level 11
Level 11

A min of 2500 W would be needed for the sup 720. (depends also on other modules installed).

A fan tray upgrade (WS-C6K-9SLOT-FAN2) can be done to provide additional cooling for equipments.

the supervisor has to be installed in slots 5/6.