HSRP Troubleshooting

o.oresotu
Level 1
Level 1

I'm presently implementing HRSP btw 2 cat 6509 (each having 1-sepervisor engine with MSFC2) switches with inter-vlan routing btw 10 vlans. However, the hosts on the vlans get frozen when the primary switch fail-over to the second switch.

What do you think is reponsible and how could i resolve this problem?.

1 Reply 1

deilert
Level 6
Level 6

DO you have port fast enabled on the switch ports that are connected to the clients off the server ?