Recommendations on Building the 7513

b.shoresh
Level 1
Level 1

Hello.

Does anyone know any kind of CCO documentation with cisco's recommendations on where to place each module on the 7513 ? Is there any prefered sequence for placing each kind of module on the 7513, so both Cybus will be occupied ?

Boaz.

1 Reply 1

rsissons
Level 5
Level 5

I am not aware of any documentation on this but it makes sense, if you have multiple high speed interfaces, to distribute them between slots 0 - 5 and 8 - 12 to make full use of both of the cybus.