Switch power problems?

Hi all,

We have a Cisco Catalyst 2960S-48FPS-L switch (in stack) up and running in our organisation. After a planned (maintenance) downtime period, this specific switch does not come up: no status/link lights; nothing. While we had moving almost all (80/90%) networkcables from the defect switch to a working one: suddenly the switch boots-up. After it boots-up, the switch (again 100% filled with phones/pc’s) is running stable for several weeks. We experience this problems two times with the same switch.

Just wondering, if anyone has experienced the same symptoms with the 2960’

We are still running IOS version 12.2(55)SE3. What do you thing: hardware or IOS-issue?

Thanks

3 REPLIES
Hall of Fame Super Gold

Can you post the output to

Can you post the output to the command "sh post"? 

 

I presume you've checked and made sure the power cable is secure and the power outlet where this switch is connected to is working fine?

New Member

Yes we checked that, here is

Yes we checked that, here is the output of the "show post" command:

Stored system POST messages:

Switch 1
---------

POST: MA BIST : Begin
  FC 1   MBIST Test Passed.
  DP Sg1 MBIST Test Passed.
  DP Xg1 MBIST Test Passed.
  NI 1   MBIST Test Passed.
  FC 0   MBIST Test Passed.
  DP Sg0 MBIST Test Passed.
  DP Xg0 MBIST Test Passed.
  NI 0   MBIST Test Passed.
  UPB    MBIST Test Passed.
POST: MA BIST : End, Status Passed

POST: TCAM BIST : Begin
POST: TCAM BIST : End, Status Passed

POST: Inline Power Controller Tests : Begin
POST: Inline Power Controller Tests : End, Status Passed

POST: Thermal, Fan Tests : Begin
POST: Thermal, Fan Tests : End, Status Passed

POST: PortASIC Stack Port Loopback Tests : Begin
POST: PortASIC Stack Port Loopback Tests : End, Status Passed

POST: PortASIC Port Loopback Tests : Begin
POST: PortASIC Port Loopback Tests : End, Status Passed

POST: EMAC Loopback Tests : Begin
POST: EMAC Loopback Tests : End, Status Passed

Switch 2
---------

POST: MA BIST : Begin
  FC 1   MBIST Test Passed.
  DP Sg1 MBIST Test Passed.
  DP Xg1 MBIST Test Passed.
  NI 1   MBIST Test Passed.
  FC 0   MBIST Test Passed.
  DP Sg0 MBIST Test Passed.
  DP Xg0 MBIST Test Passed.
  NI 0   MBIST Test Passed.
  UPB    MBIST Test Passed.
POST: MA BIST : End, Status Passed

POST: TCAM BIST : Begin
POST: TCAM BIST : End, Status Passed

POST: Inline Power Controller Tests : Begin
POST: Inline Power Controller Tests : End, Status Passed

POST: Thermal, Fan Tests : Begin
POST: Thermal, Fan Tests : End, Status Passed

POST: PortASIC Stack Port Loopback Tests : Begin
POST: PortASIC Stack Port Loopback Tests : End, Status Passed

POST: PortASIC Port Loopback Tests : Begin
POST: PortASIC Port Loopback Tests : End, Status Passed

POST: EMAC Loopback Tests : Begin
POST: EMAC Loopback Tests : End, Status Passed

Switch 3
---------

POST: MA BIST : Begin
  FC 1   MBIST Test Passed.
  DP Sg1 MBIST Test Passed.
  DP Xg1 MBIST Test Passed.
  NI 1   MBIST Test Passed.
  FC 0   MBIST Test Passed.
  DP Sg0 MBIST Test Passed.
  DP Xg0 MBIST Test Passed.
  NI 0   MBIST Test Passed.
  UPB    MBIST Test Passed.
POST: MA BIST : End, Status Passed

POST: TCAM BIST : Begin
POST: TCAM BIST : End, Status Passed

POST: Thermal, Fan Tests : Begin
POST: Thermal, Fan Tests : End, Status Passed

POST: PortASIC Stack Port Loopback Tests : Begin
POST: PortASIC Stack Port Loopback Tests : End, Status Passed

POST: PortASIC Port Loopback Tests : Begin
POST: PortASIC Port Loopback Tests : End, Status Passed

POST: EMAC Loopback Tests : Begin
POST: EMAC Loopback Tests : End, Status Passed

Switch 4
---------

POST: MA BIST : Begin
  FC 1   MBIST Test Passed.
  DP Sg1 MBIST Test Passed.
  DP Xg1 MBIST Test Passed.
  NI 1   MBIST Test Passed.
  FC 0   MBIST Test Passed.
  DP Sg0 MBIST Test Passed.
  DP Xg0 MBIST Test Passed.
  NI 0   MBIST Test Passed.
  UPB    MBIST Test Passed.
POST: MA BIST : End, Status Passed

POST: TCAM BIST : Begin
POST: TCAM BIST : End, Status Passed

POST: Thermal, Fan Tests : Begin
POST: Thermal, Fan Tests : End, Status Passed

POST: PortASIC Stack Port Loopback Tests : Begin
POST: PortASIC Stack Port Loopback Tests : End, Status Passed

POST: PortASIC Port Loopback Tests : Begin
POST: PortASIC Port Loopback Tests : End, Status Passed

POST: EMAC Loopback Tests : Begin
POST: EMAC Loopback Tests : End, Status Passed

Hall of Fame Super Gold

POST shows nothing abnormal.

POST shows nothing abnormal.  

 

You are welcome to RMA the switch and get a replacement.