Hi there,
I am currently setting up a CNA / Nexus test configuration in a Blade Server chassis.
I am using a Fujitsu CEE switch in the chassis in between CNA and Nexus.
The FJ switch is connected to the Nexus via a port-channel with 8 member ports.
And here comes my problem. I normally bind physical interfaces to my vfcs
When I now try to bind the logical port-channel interface to my vfc it says this is only possible if the channel contains not more than one member port.
If this would work all my CNA WWPNs would be mapped to a single vfc interface.
What now?
I have 18 blades each equipped with one CNA . Means on both of my Nexus fabrics I have to configure 18 vfcs and bind the 36 WWPNs manually to them.
This is really kind of annoying.
Does anybody now if this will be fixed with a future firmware release or if there is any workaround available that makes life easier?