09-23-2014 02:55 PM - edited 03-19-2019 08:39 AM
Hi, i am planning an upgrade of BE6k UC apps from 8.6 to 10.5 (CUCM,IM&P, Unity & UCCX.)
I was looking to split this over two weekends with CUCM and IM&P & Unity on weekend 1 & UCCX on weekend 2.
will UCCX 8.6 Continue to work with CUCM 10.5 during this period? i know the documentation says UCCX 8.6 is supported only with CUCM up to version 9.1
if this will not work any suggestions?
09-23-2014 04:51 PM
It won't work, unless you're fine with having no UCCX for a week, swap UCCX instead of CUC on week 1. CUC is pretty much a wildcard, you can upgrade it at anytime and it will keep on working with CUCM as long as it's 5.x+
09-30-2014 05:48 AM
I'm in the same boat as Carwyn but planning CUC later as well.
But I am wondering if the order can be: CUCM -> UCCX -> IM&P in order to have UCCX up and running earlier in our maintenance window, and complete IM&P after.
09-30-2014 07:21 AM
That's pretty much the same, you need to choose which one you need most, CUPS cannot work with CUCM 9.x+ until you upgrade to the same release and turn it into IM&P.
Discover and save your favorite ideas. Come back to expert answers, step-by-step guides, recent topics, and more.
New here? Get started with these tips. How to use Community New member guide