We shall be having power maintenance in my place of work. We would need to shut down all Cisco devices before the maintenance begins and power them back up again after. How do I shutdown modules of the Cisco 6513 multilayer switches properly before turning off the power switch?
09-24-2008 02:40 AM
Hi Austin
you need to make sure that the latest config is saved and backed up.
Also make sure that you have the ios version backed up.
Once you are done with this i dont think you have any specific procedure to shut the modules before switching the chassis off.
regds
09-24-2008 02:49 AM
From my understanding, the chassis is the back plane the holds the various modules. Do I simply carry out my back-ups and manually turn off the two power switches.
09-24-2008 03:10 AM
Hi Austin
have you installed any service modules like IDS/NAM etc., in this switch ?
I did assume end users getting connected onto the swich.
For the service modules you have shutdown either through cli or through manual intervention is reqd.
regds
09-24-2008 07:17 AM
Yes, you simply turn off the at the power switches once you have saved your config.
Note as Edwin mentioned, some of the service modules need to be shutdown before you turn off the power. You can either do this manually on the module itself ie. there is usually a shutdown button or from the CLI
6500# hw-module module
Jon
09-24-2008 07:50 AM
Thanks Jon. When power is restored, do I just power up from the power switch and assume the modules come up automatically.
09-24-2008 12:35 PM
Yes, just power up the switch. You can connect a laptop via the console connection and watch the modules come up just in case there are problems.
Jon