cancel
Showing results for 
Search instead for 
Did you mean: 
cancel
434
Views
0
Helpful
5
Replies

Unity Connection Alternate Greeting End Date Missing Day

Patrick Ward
Level 1
Level 1

Good evening, I have a Unity Connection 10.5.1.10000-7 and when someone configures an end date on there alternate greeting there is a day missing.
December only goes to 30 Days.
I looked for a BugID without success.

Has anybody come across this problem?

Thanks

1 Accepted Solution

Accepted Solutions

The Unity was updated from 10.5.1.10000-7 tot 10.5(2)SU2a last night.
The problem is now resolved.

View solution in original post

5 Replies 5

Rob Huffman
Hall of Fame
Hall of Fame

Hi Patrick,

I agree this definitely sounds like a bug to me as well but I couldn't find it either. Perhaps you can bump this thread from a few weeks back to see if you can get the TAC case # to reference in your own case;

https://supportforums.cisco.com/discussion/12712076/unity-connection-alternate-greeting-dates-are-wrong

Cheers!

Rob

We will proceed with the update to SU2a as suggested by Cisco.
I will let you know the outcome.
Thanks.

The Unity was updated from 10.5.1.10000-7 tot 10.5(2)SU2a last night.
The problem is now resolved.

Hi Patrick,

Thanks for posting back with your results! (+5) This type of kind gesture is greatly appreciated.

Cheers!

Rob

Patrick Ward
Level 1
Level 1

The Unity was updated from 10.5.1.10000-7 tot 10.5(2)SU2a last night.

The problem is now resolved.